Dependencies & Critical Path

Dependencies​

Each milestone can declare predecessor links — in the grid's Dependency column or the dialog's Dependency tab — using MS-Project-style types, with an optional lag:

TypeMeaning
FSFinish-to-Start — the predecessor must finish before this task starts
SSStart-to-Start — both tasks start together
FFFinish-to-Finish — both tasks finish together
SFStart-to-Finish — the predecessor's start drives this task's finish

The Dependency tab lists predecessors with ID / Name / Type / Offset (the lag). The Gantt draws dependency links between the bars on the timeline.

Critical Path​

Click Critical Path on the toolbar to highlight, in red, the tasks whose slip would push the project end date back:

Critical path highlighted

Click the toggle again to return to normal styling.